Tub | Shower Combo
With favorable conditions, it takes approximately 9 days for a Standard Tub to be installed with your favorite choice of Tile. Be sure to keep in mind, actual days vary.
​

01
Demo | Frame
Approx. 2 Days
Removing the old polystyrene 3-piece tub surround. Then framing the niche.
02
Set Tub | Waterproof
Approx. 2 Days
Setting HardieBacker Cement Board with HydroDefense Technology. After all the framing is complete.


03
Tile | Grout
Approx. 3.5 Days
Installing aspen gris 12”x 24” matte floor and wall ceramic tile.
04
Clean | Walk Through
Approx. 1 Day
After all tile and grout has cured, is it cleaned and sealed. Then fixtures are installed.


Tub | Shower Combo Package
All Materials and Labor Included
Silver
7,000$Waterproof paneling screwed to studs or adhered to shower walls with adhesive | 10+ Color OptionsÂ- Tub Surround Paneling Resembling Tile
- Standard Tub
- New Shower Fixtures
Gold
13,000$A Shower Upgrade That Will Stand Out In Your NeighborhoodÂ- Waterproof System
- Standard Tub
- Standard Shower Niche
- Standard Tile Pattern
- Tile to Ceiling in Shower Area
- One Shower Head
- New Shower Fixtures
- Recessed Lights in Shower
- Best Value
Diamond
19,000$The Shower You've Been Dreaming About With All Your Favorite FeaturesÂ- Waterproof System
- Luxury Tub
- Custom Niche
- Luxury Tile Patterns
- Tile to Ceiling in Shower Area
- Multiple Shower Heads
- New Shower Fixtures
- Recessed Lights in Shower w/ Dimmer
- Mitered Tile Edges
- Accent Wall
- European Shower Doors
- 3D Model Design
Approx. 10 Days
Approx. 9 Days
Approx. 4 Days
bottom of page